Steve Gummer and Tom Knox look into the Ofgem decision on a round of reform to the UK's energy grid.

On 15 April 2025, Ofgem published its decision to approve the Target Model Option 4+ (“TM04+”) package of reforms to the UK’s electricity grid connection regime.

This decision marks a significant step forward in the country’s efforts to accelerate decarbonisation and achieve its target of 95% carbon-free electricity by 2030.

The TM04+ reforms directly respond to the Government’s Clean Power 2030 Action Plan, which identifies the need for “fundamental reform of the connections process” as critical and urgent.

By ensuring that viable, strategically aligned energy projects are prioritised for connection to the electricity grid, the TM04+ framework is expected to unlock capacity for projects essential to the UK’s energy transition.

Addressing Grid Congestion and Speculative Projects

Before the introduction of TM04+, projects could secure a grid connection slot or join the connection queue without needing to demonstrate readiness or deliverability.

This has resulted in a connection backlog of commercially unviable projects (sometimes referred to as ‘zombie projects’), which in turn block viable, generation or demand ready projects from securing a connection to the grid.

The TM04+ reform package replaces this outdated “first come, first served” system with a more structured, criteria-based approach to managing the connection queue.

Under the new model, projects will be assessed against two key criteria:

Two-Gate Connection System

Projects will be allocated into one of two categories, Gate 1 or Gate 2, depending on how they meet the following criteria:

  1. Readiness – Is the project sufficiently advanced and viable for development?
  2. Need – Does the project align with the strategic system needs as defined by government priorities and the Clean Power 2030 objectives? These strategic alignment criteria are set and will be periodically updated by the UK Government to reflect evolving energy policy.

The assessment of whether a project is ‘needed’ might consider a range of factors including:

This assessment will be undertaken by the National Energy System Operator (“NESO”) for transmission-level connections, and by the relevant Distribution Network Operator (“DNO”) for distribution-level connections.

While DNOs will use mirrored criteria, these may be tailored to reflect local network needs and operational considerations. For projects with a transmission impact, NESO and the DNO will coordinate the assessment, ensuring consistency.

The difference between the ‘Gate Offers’ and connection rights are as follows:

How Gate Offers Will Be Issued to New and Existing Applicants

Both new and existing applicants will have opportunities to apply for Gate 2 offers under TM04+. All projects, regardless of when they entered the queue, will need to demonstrate that they meet the required Readiness and Need criteria.

Existing projects already in the connection queue will be invited to apply for reassessment. If their application is successful, and the project is deemed both ready and needed, they will receive a Gate 2 offer.

However, if they fail to apply, withdraw from the reassessment process, or are not assessed as meeting the criteria, they will automatically fall into Gate 1 and receive only an indicative offer.

New applicants will be assessed from the outset under the TM04+ framework.

Which Projects are Subject to the TM04+ Reforms?

Generation and Storage Projects

TM04+ applies to all generation and storage projects that require a Transmission Impact Assessment (TIA). In England and Wales, this includes projects with a capacity of 1 MW or greater, although this threshold may be revised in future updates to the framework.

Demand Projects – Distribution Level

New demand projects connecting solely to the distribution network generally fall outside the scope of TM04+. These projects will continue to follow the existing DNO-led application and connection process.

Demand Projects – Transmission Level

Large demand projects connecting directly to the transmission network will be subject to the TM04+ framework. These projects must satisfy both the readiness and need criteria, although they are more likely to be classified as “needed” due to their role in balancing system demand. Projects meeting the readiness threshold are expected to receive Gate 2 offers promptly.

Projects Connected at a Distribution Level with Transmission Impact

Some distribution-connected projects may still have a significant effect on the transmission system due to their size, location, or operational characteristics. These projects, although physically connecting at the distribution level, must undergo a Transmission Impact Assessment (TIA) and will fall within the scope of TM04+.

This includes:

Such distribution-connected projects with a transmission impact will need to demonstrate both readiness and strategic alignment in line with the TM04+ Gate 1/Gate 2 framework. The relevant DNO will manage the connection application, but NESO will review the project’s transmission impact and contribute to the assessment of its priority.

In practice, this means that:

This change ensures that all projects, whether connected at the transmission or distribution level, are evaluated based on their actual impact on the electricity system, supporting a fairer, more efficient, and strategically aligned connections regime.

Steve Gummer is a Partner and Tom Knox is an Associate at Sharpe Pritchard LLP.


For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.

sharpe edge 600x100

This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email This email address is being protected from spambots. You need JavaScript enabled to view it..