David Owens and Elizabeth Withers explore recent developments in construction contract case law.

 

In this article, we build upon the insights shared in our previous article, which outlined key considerations when negotiating standard form construction contracts, discussing lessons learnt from a recent case from the Technology and Construction Court (TCC) involving electronic and hard copy versions of the same document:

John Sisk and Son Limited and Capital & Centric (C&C)(Rose) Limited [2025] EWHC 594

Background to the dispute:

This case involved a JCT D&B 2016 contract for the design and construction of substantial works at Weir Mill, Chestergate, which contained substantial amendments.

A dispute arose as to who is contractually responsible for the risks associated with the ground conditions and the existing structures on the site, including their ability to support and/or facilitate the proposed works.

Prior to the proceedings, there had been an adjudication whereby the adjudicator found in C&C’s favour, concluding that “…the responsibility for ground conditions including the identification of the basements, structures, voids, compressed structural elements and obstructions under the existing West Mill was solely Sisk’s risk”.

As a result, this risk meant that Sisk was unable to claim an extension of time and/or any additional costs it incurred.

In a Part 8 claim, HHJ Stephen Davies held that on a proper interpretation of an amended JCT DB 2016, the risk of the unsuitability of existing structures was an employer risk. In doing so, the judge reached the opposite conclusion from the adjudicator.

Key contractual provisions and their interpretation

The dispute hinged on the interpretation of clauses 2.42.1 to 2.42.4 of the amended JCT contract and the relationship between those provisions and documents referred to as “Clarifications” in the Employer’s Requirements.

Clauses 2.42.1 – 2.42.3: Contractor risk

Clause 2.42.4: A limited carve-out

Conflicting documentation

An issue then arose due to the existence of two documents:

C&C argued that the Tender Submission Clarifications formed part of the contract documents and supported the adjudicator’s conclusion. However, the judge disagreed.

The court’s findings

The court held that:

Key takeaways

As discussed in our previous article, when negotiating construction contracts, clarity and consistency remain important considerations, as well as the fact that parties cannot rely on negotiation history where this is not reflected in a proper interpretation of the contract. Building upon this consideration, the following takeaways are key in light on the Sisk v C&C case:

Conclusion

The Sisk v C&C decision is a reminder for parties involved in construction projects of the importance of clarity and consistency in contract drafting. Where standard forms are amended, those amendments must be precise, and the inclusion of additional documents must be managed with care.

David Owens is a Partner and Elizabeth Withers is a Trainee Solicitor at Sharpe Pritchard LLP.


For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.

sharpe edge 600x100

This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email This email address is being protected from spambots. You need JavaScript enabled to view it..