Steve Gummer and Shyann Sheehy talk through the recent Construction Leadership Council guidance on a ‘Golden Thread’ of information as part of a new regulatory regime for Higher-Risk Buildings.

The Building Safety Act 2022 (“BSA 2022”) together with subsequent secondary legislation, introduced a new regulatory regime for Higher-Risk Buildings (“HRB”) in England. Part of the new regime is a requirement for a ‘Golden Thread’ of information.

On 27 August 2024, the Construction Leadership Council (“CLC”) published “Delivering the Golden Thread: Guidance for dutyholders and accountable persons” (the “Guidance”), which sets out further detail on its purpose, and practical steps for compliance. The Guidance is divided into three main sections: summary of the fundamentals of the Golden Thread; the Golden Thread requirements during the design and construction phase; and the Golden Thread requirements during the occupation phase.

The Guidance is intended to be a dynamic document, in that CLC is encouraging feedback on it. We explore below the Guidance related to the design and construction phase of an HRB.

A full copy of the Guidance can be downloaded here.

What is the Golden Thread and what is its purpose?

The BSA [1] places a legal duty on dutyholders and accountable persons to keep and maintain the Golden Thread. It is a digital record of the HRB which is to be maintained throughout the building lifecycle.

At its core, the aim of the Golden Thread is to help ensure that building safety risks are being managed for the safety of those living and using the HRB. It is intended to deliver “accurate information about the building to those that need it and to support those people to use that information to comply with building regulations (in design and construction) and managing spread of fire and structural risk (in occupation)” [2].

What Golden Thread information is needed at the design and construction phase of an HRB?

The requirement to create and maintain a Golden Thread of information extends to works creating a new HRB (this includes building a new or changing the use of an existing building in order that it becomes an HRB), as well as works to an existing HRB.

Those responsible for creating, updating and maintaining the Golden Thread during this phase includes the appointed dutyholders under the Building Regulations being – client, principal contractor and principal designer.

The client dutyholder is responsible for providing the electronic facility for storing the Golden Thread and the procedures that allow access and maintenance of it.

Even before work starts, the Golden Thread must contain information that can demonstrate that the HRB, when built, will satisfy the functional requirements of Building Regulations and that the building work will be managed to ensure it meets the design.

The information to be stored on the Golden Thread forms part of the ‘accompanying documents’ needed for building control Gateway Two approval. These specific documents are set out in the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 and includes:

During construction works, the Guidance has made it clear that “Sufficient evidence must be captured during construction to show: how the building work conforms to the design that was approved, including any approved changes; and how the building satisfies all the applicable functional requirements of the building regulations” [16]. The Golden Thread is therefore an evolving repository of information on that HRB and the dutyholders need to work together to ensure that record keeping is accurate and up to date.

Upon completion of the construction phase, these documents will also form part of the application for completion certificate Gateway Three approval to the BSR.

Once Gateway Three approval has been obtained the HRB can be occupied and the Golden Thread will be passed to the accountable person/principal accountable person to manage.

Implications of the Guidance for the Construction Industry

This Guidance will likely become a cornerstone document that will help shape the form and structure of the Golden Thread information.

a. Construction Contracts – JCT 2024

Following the on-going release of the JCT 2024 suite of contracts it will be a watching brief to see how the industry responds to the Guidance and the new clause 2.26.8 as set out in JCT Design & Build form (and also mirrored in some of the other JCT 2024 standard forms).Clause 2.26.8 provides that “…the publication of any guidance, by the United Kingdom Government or any of the devolved administrations…or in the case of guidance by the Construction Leadership Council or its successors” [Emphasis added] constitute Relevant Events under the contract.This means that if the contractor can show that the Guidance has impacted upon the execution of the construction works relating to an HRB, this may entitle the Contractor to claim for an extension of time to carry out the works under the contract.Furthermore, if clause 4.21.7 is selected within the Contract Particulars, this Guidance would also be considered a Relevant Matter. This would then entitle the contractor to make a claim for loss and expense.Employers should be mindful of this when considering amendments to the JCT 2024 suite and careful consideration should be given to the inclusion and wording of these clauses during the contract negotiation process to identify, apportion and mitigate potential liabilities.

b. Resourcing

It should not be underestimated the time and resources needed to adequately procure an electronic facility to house the Golden Thread. For clients with large HRB stock, consideration will need to be given as to how best to create, operate, manage and maintain the Golden Thread ensuring compliance whilst inevitably keeping within tight budget constraints.

c. Communication

It is expected that the Golden Thread is an information source utilised daily. Internal client teams and the dutyholders all feeding into the Golden Thread will need to have clear understanding on the impact of their work on the HRB and the ongoing requirement to ensure the accuracy and relevance of the information being stored on it.

Steve Gummer is a Partner and Shyann Sheehy is a Paralegal at Sharpe Pritchard LLP.
 
[1] See s.33, s.88 and s.90 of BSA and the requisite dutyholder responsibilities set out in the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023

[2] Page 12 of the Guidance

[3] Page 36 of the Guidance

[4] Page 36 of the Guidance

[5] Page 30 of the Guidance

[6] Pg 37 of the Guidance

[7] Ibid

[8] Ibid

[9] BS 9991 Fire safety in the design, management and use of residential buildings – code of practice: sets out good practice in relation to building safety risks relating to fire

[10] BS 9792 Fire risk assessment – housing – code of practice (currently under development): sets out good practice in relation to building safety risks relating to fire.

[11] BS EN ISO 31000 Risk management guidelines: sets out good practice in relation to risk management

[12] BS 8644-1 Digital management of fire safety information – code of practice: management of digital asset information in the built environment, particularly fire safety information

[13] Page 38 of the Guidance

[14] Page 32 of the Guidance

[15] Pg 38 of the Guidance

[16] Page 25 of the Guidance


For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.

sharpe edge 600x100

This video is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email This email address is being protected from spambots. You need JavaScript enabled to view it.