Winchester Vacancies

Council submits £130m claims in High Court bid to recover costs under housing estate maintenance PFI

Camden Council has submitted claims to the High Court to recover costs from the contractor PFIC (Partners for Improvement in Camden) and its principal subcontractors, who previously had responsibility for refurbishment and maintenance of the Chalcots Estate, under a private finance initiative agreement.

The London borough said the claims had been submitted against PFIC – currently in liquidation – and Rydon Construction Ltd, Rydon Maintenance Ltd, Faithful + Gould Ltd. and United Living South Limited.

It is seeking to recover costs the local authority says it incurred as a result of having to address multiple fire safety failings at the Chalcots Estate and the related evacuation of its residents in June 2017.

The council is seeking to recover costs in relation to the evacuation of Chalcots residents, the employment of fire marshals and security staff during the evacuation and beyond, its repairs to make good inadequate internal fire stopping, inadequate fire doors and other serious defects inside the Chalcots towers and the removal of combustible aluminium composite material cladding from the blocks’ outer façade.

A Camden Council spokesman said: “We were let down by PFIC, Rydon and other contractors. The PFI agreement for refurbishment and maintenance of the Chalcots Estate was entered into in good faith and fundamental to this was our expectation that the Chalcots towers would be safe for our residents. We should not have been put in a position where we were left with no option but to evacuate residents from their homes on a Friday night.

“Our absolute priority is the safety of our residents so, upon discovering serious deficiencies in the work and materials used by our contractors, we stepped in with new contractors, to complete works that would allow Chalcots residents to start to return safely to their homes within four weeks and, within six months, had fully removed cladding from the towers.”

The spokesman added: “The costs of the supporting residents during the evacuation and level of work required at the Chalcots made a major impact on our reserves. Clearly, it would not be right for residents and, by extension, the public purse, to foot the bill for what has been a private contractor failure.”

He acknowledged that in October 2018 the council secured £80m from the Government to fund the replacement of cladding on the Chalcots Estate, but said that this only covered part of the costs. “[It] still leaves us with substantial losses that we are determined to recover.”

The spokesman continued: “[These] claims are submitted following two years’ examination of historical agreements, contractual responsibilities and works completed during the period in which we had a contractual relationship with PFIC. Following this review, we are clear about where responsibility lies for the range of fire safety defects at the Chalcots which led to the evacuation and its associated costs.”

Rydon and Faithful + Gould declined to comment. United Living has been approached for comment.

Sponsored Editorial

Need a transcript or recording?

Are you a Paralegal or a Legal Officer? Have you been asked to obtain a transcript of a recording for use as evidential material? Wondering where to start? Don’t worry – we speak to people in your position every single day – and we’ll be happy to help you too. Whether or not you choose to use our…