Sharpe Edge features news, views and analysis from our team of specialist local government lawyers working at the heart of the latest legal developments. Sharpe Edge platform is also the only place where local government lawyers can get e-access to two law books by our Head of Local Government Rob Hann: The Guide to Local Authority Charging and Trading Powers (‘LACAT’) and The Guide to Local Authority Companies and Partnerships (‘LACAP’).

 

                                                                                                  

Slide background

The Long Goodbye to the PFI

Icons HouseRob Hann, Sharpe Pritchard’s Head of Local Government takes a look at the House of Common’s Public Account Committees’ recent report into the pending expiry of PFI contracts which contains some interesting recommendations….

Hot on the heels of last year’s NAO report into the expiry of PFI contracts, Managing the expiry of PFI contracts - National Audit Office (NAO) Report the House of Commons Public Accounts Committee have now published their report and findings (‘the PAC report’) into the same issue having taken evidence from a number of sources including HM Treasury, the Infrastructure Projects Authority (the IPA) several local authorities and Local Partnerships (the successor central body to 4ps/PUK which is now owned by the LGA and HMT and which has responsibility for local government PFI, amongst other things). In an earlier article I commented on the NAO recommendations.

The interest now being shown by central Government into the challenges faced by many diverse public bodies as these hugely complex PFI contracts head toward contract maturity, whilst heartening, merely scratches the surface of the problems ahead for public body parties to PFI contracts.

As the PAC have noted: “Over the next 10 years, an estimated 200 PFI projects will come to an end, representing £10 billion of assets. In most cases, when a PFI contract expires, the assets will transfer to the public sector. The process is complex and requires the public body (the authority) that entered into the original contract to take several actions in advance of expiry. First, the authority has a duty to ensure the private company has completed any scheduled or reactive maintenance, including any rectification work required to bring the asset up to the condition stipulated in the contract.

"Second, the authority needs to decide if the assets and services are required after expiry and, if so, how the asset will be maintained, and the services provided.”

It is the second task identified above which is of particular concern and would need addressing as a priority, well in advance of expiry. Of course, it could be argued that inheritance of a fully maintained and paid for asset at the end of a long-term contract is a benefit to the public body and was always the outcome envisaged at contract signing? But whether, in reality, it is a benefit or else, becomes an expensive additional burden on public finances which the entity in question can ill-afford, will be something the authority will need to give serious consideration to.

When PFI was rolled out across local government, local authorities were incentivised to consider PFI because central government (through PFI credits and later PFI grant) provided much needed additional funding to help meet the cost of supply of those ‘asset intensive services’ for the contract term. However, once the PFI contract expires, the additional ring-fenced PFI funding support from central government to the authority (pretty much anyway) ceases. So local authorities will be faced with inheriting not just the assets (in whatever condition they arein at that stage) but also the liabilities which go with the upkeep of those assets, only this time, without extra central government grants to help meet those costs. Affordability is, therefore, a major issue.

One approach I was hoping the Government would take (post-Covid pandemic and to help with re-investment costs) would be to announce a new funding programme specifically aimed at refreshing legacy PFI estate and recognising the need for on-going maintenance and refresh. However, as yet, no such initiative appears to be on the horizon.

In the absence of any additional funding, the public body will need to undertake an options appraisal to explore which of several alternative courses of action open to it are most suitable. The options available will depend on the sector, the assets in questions and the needs of the public body going forward. If the public body doesn’t wish to bring the assets under direct local authority/public sector control, a decision will need to be made as to when and how to go out to the market, well in advance of contract expiry, to seek a new service provider.

Any such procurement exercise would need to be timed carefully so as to dovetail with expiry and enable the new provider to take over the responsibility for servicing the assets. But is there a market of new providers out there ready and willing to step into the shoes of existing PFI contractors who have been running the service for 20-25 years? What about the incumbent provider? – will they want to retender and if so, will that prove to be a disincentive to any other party taking the time, cost and effort to bid?

What about the procurement process itself? In the past, significant resources were provided by the central bodies in terms of standard form contacts, the development of standard contract terms (known as ‘SoPC’,) procurement guidance and templates but is such support likely to be forthcoming in future from the central bodies? A helpful step (not contemplated by the PAC) would be for the IPA/HMT to produce a fresh iteration of SoPC which would provide a strong starting point for commercial negotiations going forward in a post-pandemic, post Brexit environment. What approach would the market now take on existing SOPC 4 drafting for force majeure and insurance for example? These sorts of issues need to be addressed by the central bodies now (HMT, IPA, Local Partnerships etc) and for the benefit of all sectors.

The recent Green Paper on public procurement flagged the fact that procurement rules and processes are likely to change over the course of the next few years. Will a new generation of service providers be encouraged to bid if there is no certainty that public bodies will have the budget and funding to pay for such services? Will they be willing to bear the costs, time and effort involved in submitting bids in the brave new world of reformed UK public procurement processes?

One of the PAC observations is around the needs and demands public sector bodies have for assistance from external consultants. There are many consultants who have good and detailed knowledge and experience of PFIs and who could play a valuable role if they could be accessed easily and quickly by those who need them. The IPA says it is ‘building capability’ and is recruiting additional staff to develop a central pool of resources but so far this consists of just 17 people - not enough resource to support all 700 contracts.

One alternative approach would be for the central bodies to pre-qualify a cadre of experts across the professional disciplines by establishing a framework with call-off arrangements. This would provide public bodies with choice whilst controlling costs and avoiding the need for each authority to go separately to the market.

As regards what sort of support is available from the central bodies to the public authorities involved the PAC noted that: “Each individual authority is responsible for managing the expiry of its PFI contract. When an authority needs help, support is often lacking, or it is not always clear how to access it, with varying degrees of support available from multiple sources across central government. The IPA is building capacity and plans to provide support and advice via its contract management programme. Local Partnerships provide training courses and lessons learned examples when requested, while the sponsoring department is responsible for drawing on the expertise at the IPA.”

The PAC wanted more information from the IPA/HMT on who provides what support to whom.

One omission from the PAC report was the fact there was no mention of the Gateway review process which, in the past, was a common method employed by the central bodies to take the temperature of a project and to find out a lot of key information about a contract in a short intense review. Gateway reviews in the past were done at crucial stages of a project’s gestation to provide some comfort that they were ready to proceed to the next step (here - its journey towards expiry). Perhaps gateway reviews have fallen out of fashion? If so, that is an opportunity missed to get under the skin of some of these complex arrangements quickly.

Resolving disputes prior to contract expiry is mentioned by the PAC as a particular area of difficulty. Whilst the standardisation of PFI Contracts (SoPC) contained some model form drafting that developed and improved over time, DRP is inherently complex, relies on co-operation by both parties to set up a DRP panel, takes an awful long time and is prohibitively expensive for many authorities. The PAC tasked the IPA with publishing a disputes protocol, outlining how disputes can be escalated by authorities, and the steps that can be taken to ensure disputes only need to be resolved by the courts as a last resort.

Protocols have been used to good effect before in PFI (e.g. gain-share on refinancing and change protocols were introduced in later iterations of the SoPC contract templates). However, it is questionable what impact such a protocol will have on contractors who have their sights fixed on exiting without resolving such disputes (if that approach is in their financial interests).

One of the issues the PAC does recognise is the potential for some PFI investors’ ability to withhold crucial information about the contract from the public body. The PAC has tasked the IPA to provide (again within 3 months) the steps it is taking to ensure PFI investors are being fully transparent and compliant with contracts, and what action, if any, it will take if an investor if found to be deliberately non-co-operative.

One recent development might assist here (and may give the IPA some ‘teeth’) is to look in detail at the proposals in the Government’s Green Paper on transforming procurement which included recording and permitting past poor performance of a public contract to be a discretionary exclusion ground for new contracts. Why not use the expiry of PFI and the conduct and performance of contractors, as a trigger for HMT to commission independent reviews of these contracts as they head towards termination with a view to recording outputs for this purpose? Even the threat of this as a potential sanction might help bring the (hopefully few) unscrupulous parties back into line.

Rob Hann was head of legal at 4ps/Local Partnerships between 1996 and 2016 and (amongst other things) he helped develop and deliver the roll out of the PFI across local government including templates, model form sector specific contracts and the local government input to SoPC. He is now Head of Local Government at Sharpe Pritchard. He can be contacted at This email address is being protected from spambots. You need JavaScript enabled to view it..


For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.

sharpe edge 600x100

This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email This email address is being protected from spambots. You need JavaScript enabled to view it.

LACAT BookFREE download!

A Guide to Local Authority Charging and Trading Powers

Written and edited by Sharpe Pritchard’s Head of Local Government, Rob Hann,

A Guide to Local Authority Charging and Trading Powers covers:

• Updated charging powers compendium          • Commercial trading options

• Teckal ‘public to public’                                    • Localism Act

FREE DOWNLOAD

LACAT BookAvailable to buy:

A Guide to Local Authority Companies and Partnerships

An invaluable, comprehensive toolkit for lawyers, law firms and others advising
on or participating in Local Authority Companies and Partnerships”

- Local Authority Chief Executive

BUY NOW

  More Articles

Icons Court

Climate emergency or climate catastrophe?

Rob Hann asks how central & local government departments and councils can work together more effectively to combat the challenges to achieve net zero by 2050.
Icons Court

Big Problems Need Radical Solutions – Time to Play Monopoly with District Heating?

Steve Gummer examines how local authorities might make district heat networks a reality.
<a href=

The Judicial Review and Courts Bill

The Judicial Review and Courts Bill was introduced to the House last week on 21 July 2021. William Rose and Anna Sidebottom discuss the potential impact of the bill.
<a href=

Liquidated damages and termination

Clare Mendelle, Francesca Gallagher and James Goldthorpe provide an outline of the Supreme Court's recent decision in Triple Point Technology vs PTT Public Company Limited.

Mandatory Vaccination for Care Home Workers in England

The Government has announced that people working in care homes in England must be fully vaccinated against Covid-19 from October 2021, unless they have a medical exemption, write Rachel Murray-Smith and Francesca Gallagher.
Icons Court

Transparency in Procurement: Procurement Policy Note (“PPN”) 07/21

Julie Lau, Clare Mendelle and Beth Edwards outline the new regime for publishing procurement notices post-Brexit
Icons Court

When procurement law and contracts for interests in land meet

Colin Ricciardiello provides a case law update examining cases that have examined the overlap between a requirement to procure and a contract for the disposal of an interest in land.
tb w74 h74 crop int a734a5aec8e0dcb7849ee8ebeb84a53d

UK granted data protection adequacy decision

Charlotte Smith summarises the new data protection adequacy decision.

First Impressions on the New Subsidy Control Bill

Last week the Government published its new Subsidy Control Bill. The Bill represents a significant shift in the way in which subsidies are assessed and also provides some clarity about the regime that will replace the EU State aid regime, writes Peter Collins.
Icons Court

Managing new enforcement powers for councils under the Traffic management Act 2004

Rob Hann considers the recent legislative changes to traffic management in England, including the introduction of Clean Air Zones and widening local authorities enforcement powers for moving traffic offences.
Icons Court

Implementing Net Zero: Taking account of Carbon Reduction Plans in the Procurement of Major Government Contracts

The Government recently published the Procurement Policy Note 06/21. This will require suppliers bidding for major government contracts to provide a Carbon Reduction Plan at the selection stage and commit to achieving Net Zero by 2050, writes Clare Mendelle and James Goldthorpe.
tb w74 h74 crop int a734a5aec8e0dcb7849ee8ebeb84a53d

Public Procurement Update June 2021

On 3 June 2021, the Government issued the National Procurement Policy Statement (NPPS), and the associated Procurement Policy Note (PPN). George Dale explains what each document does.

What a bind: Section 106 planning obligations where there are multiple land interests

Rachel Lee and Christos Paphiti consider whether the case of R (on the application of McLaren) v Woking Borough Council impacts upon local planning authorities (LPAs) ability to properly consider the land interests and parties as regards to performance of specific obligations.
Icons Court

The use of experts only works when everyone plays by the same rules

Colin Ricciardiello looks at the use of expert witnesses in the wake of an important recent decision.
Icons Court

Unlawful Award of Contract

The High Court has ruled that the Minister for the Cabinet Office, Michael Gove, broke the law by giving a contract to a market research company, Public First, who are run by long-time associates of his. Anna Sidebottom, Francesca Gallagher and Clare Mendelle report.
Icons Date

Time after time: extending time for determination of a prior approval application

Rachel Lee and Christos Paphiti examine the time period for determination of Prior Approval (‘PA’) applications and explore how a local authority can extend the time period for determination.
Icons Date

The Cram Slam – Part 26A Restructuring Plans and Commercial Leases

David Nelson looks at the impact on landlords of a controversial High Court decision to allow a restructuring plan for a chain of health clubs.
Icons Court

The limits of an adjudicator's jurisdiction

Dr Paul Hughes and Anna Sidebottom look at the effect of Prater v Sisk [2021] on the ability of an Adjudicator to rely on previous 'out of jurisdiction' decisions between the same parties
Icons House

The Queen’s Speech and Judicial Review

Colin Ricciardiello looks at the likely effects of the government's proposed changes to the judicial review process.
Icons House

The Subsidy Control Bill

Ryan Copeland and James Hughes analyse the main provisions of the Subsidy Control Bill announced in the recent Queen’s speech.
Icons Court

Councils unable to hold meetings remotely from 7th May

Radhika Devesher considers the fallout from the High Court's decision that online council meetings cannot continue past 7th May and outlines the practical steps that councils can take to ensure that the decision-making process is not adversely affected.
Icons Court

You can’t claim that! Court finds exclusion clauses work just like any other clause

The recent case of Mott MacDonald Limited v Trant Engineering Limited serves as a timely reminder that exclusion clauses in construction contracts can and do work and will be enforced by the courts to prevent what may otherwise be valid claims write Clare Mendelle and James Goldthorpe.
Icons Date

Sparks Flying: Increasing Network Connectivity For Tenants

Lillee Reid-Hunt, James Nelson and Natasha Barlow look at the potential impact of The Telecommunications Infrastructure (Leasehold Property) Act 2021 on reducing delays in the installation of telecommunications equipment to leasehold properties.
Icons House

Subcontract held to govern works commenced before execution

Clare Mendelle and James Goldthorpe examine a case which considered which terms governed liability for works carried out prior to the execution of a contract.
Icons Court

No overlap between substance and jurisdictional issues

Clare Mendelle and James Goldthorpe examine the implications of Ex Novo Limited v MPS Housing Limited [2020] EWHC 3804 (TCC)]
Icons Court

Home is where the heart is

Bernadette Hillman and Christos Paphiti outline the new permitted development right and what it means for the property sector and planners
Icons Date

Can a worker get paid for sleeping?

Some jobs such as care workers, security guards and nightwatchmen require the individual to work night shifts where they may, with the approval of their employer, sleep during some or all of the shift, but nevertheless remain on standby during that time.
Icons Date

Can you decline to sponsor skilled workers under the new immigration rules?

Is there an obligation to consider resident workforce prior to employing migrants? Julie Bann and Aleksandra Wolek report.
Icons Court

Changes to the Electronic Communications Code

The Department for Digital, Culture, Media and Sport has commenced a consultation on changes to the Electronic Communications Code 2017 (the “Code”). James Nelson, Lillee Reid-Hunt and Natasha Barlow report.
Icons Court

The Heat Networks (Scotland) Bill

Until last week the heat network sector in Scotland was not specifically regulated. The recent Heat Networks (Scotland) Bill seeks to rectify this by creating a regulatory framework and licencing system designed to encourage the increased use of heat networks.
Icons Date

A step in the right direction

Rob Hann and Juli Lau outline Sharpe Pritchard’s response to the Government’s Green Paper on reforming the ‘outdated’ public procurement regime.
Rob Hann

Life on the Edge!

This week sees the launch of Sharpe Edge – the home of Sharpe Pritchard on Local Government Lawyer. We have created Sharpe Edge for local authorities who are looking for ways to help their communities rebuild and regenerate following the devasting impact of the Covid-19 Pandemic.
Icons Court

Teckal and Beyond….

In this article Rob Hann, Sharpe Pritchard’s Head of Local Government, takes a look at what isn’t covered in the recent Green Paper on Transforming the UK’s Public Procurement rules, namely the exception contained in regulation 12 of the Public Contracts Regulations 2015 (PCR 2015), commonly referred to as the Teckal exemption and asks whether Teckal is ‘fit for purpose’ in a post Brexit, post pandemic environment?
Icons Court

Jurisdiction Clauses & Enforcing Adjudication Decisions

The case of Motacus Constructions Ltd v Paolo Castelli Spa [2021] EWHC 356 (TCC) confirms adjudication’s status as an interim-binding measure and reinforces its importance as a dispute resolution forum in the construction industry.
Icons Date

Procurement in an Emergency – Requirements for Transparency

Public procurement has never had such a high profile as it has in recent months and most especially since the decision in Good Law Project and Others v Secretary of State for Health and Social Care ([2021] EWHC 346 (Admin)). However, in practice, has anything changed?
Icons Court

Disallowed Costs, Definitions and Default

The recent case of ABC Electrification Limited v Network Infrastructure Limited [2020] EWCA Civ 1645 saw legal practitioners jousting over the definition of a solitary word – namely, “default”. In this case regarding the scope of ‘Disallowed Costs’ in a common rail industry contract, the Court of Appeal issued a stark reminder to contractors that the meaning of individual words can be the difference between millions of pounds.
Slide background