- Details
Get the timing right! Terminating a JCT contract
The recent High Court case of Andrew Bellis v Sky House Construction Ltd provided clarity on termination provisions in JCT contracts, and specifically when a termination notice can be issued, write Michael Comba and Beth Edwards.
Terminations always have tricky procedures, even if it is cut and dry that a contractor is in breach and a right to terminate has arisen. Issuing the notices at the right time is always a key part of this.
Background
Mr. Bellis had entered into a JCT Minor Works Contract (2016 Edition) with Sky House Construction Ltd to build a house extension. The contract contained the following process for termination:
- When a default occurs before practical completion, the employer may issue a default notice;
- If the default in question continues for seven days, the employer may issue a termination notice to the contractor. This can be issued on the expiry of the seven days, or within 10 days of this.
Clause 1.4 of the contract stated that “Where under this Contract an act is required to be done within a specified period of days after or from a specified date, the period shall begin immediately after that date.”
Mr Bellis had served an initial notice by hand on 1 September, which was followed by a termination notice on 8 September. Sky House commenced an adjudication for wrongful termination
The adjudicator found that Mr Bellis had issued the notice of termination too early (one day before he was entitled to do so), and in doing so had repudiated the contract. He was thereafter liable to pay over £30,000 to Sky House in damages.
Mr Bellis referred the issue to court, arguing that the adjudicator had erred in concluding that the contract had been terminated wrongfully.
Judgment
The court agreed with the adjudicator and accepted Sky House’s argument that the contract required seven “clear” days’ notice of a specified date, meaning the termination notice should only have been issued on 9 September. The use of clear days is a common approach to the calculation of time periods, for example it is used under the Civil Procedure Rules, and there is no suggestion in the JCT drafting that it should not be used here.
The court rejected Mr Bellis’ argument that the expiry of seven days was not a “specified date” referred to in clause 1.4, as it was not specifically referred to in the Contract Particulars. This interpretation would greatly reduce the effect and utility of clause 1.4, which could not have been what was intended in the drafting. Additionally, if Bellis’ interpretation had been correct, it could have led to a situation where Sky House had less than seven days to rectify the default; this is already a short period for defaults to be rectified and, from a practical perspective, should not be reduced even further.
Commentary
Applicable across the JCT suite, this case underlines the importance of complying with the JCT timelines.
A cautious approach is recommended for employers seeking to terminate and to double and triple check a right to terminate has procedurally arisen. That goes alongside any other procedural requirements, such as using the correct method and address of service.
For further insight and resources on local government legal issues from Sharpe Pritchard, please visit the SharpeEdge page by clicking on the banner below.
This article is for general awareness only and does not constitute legal or professional advice. The law may have changed since this page was first published. If you would like further advice and assistance in relation to any issue raised in this article, please contact us by telephone or email
|
Click here to view our archived articles or search below.
|
|
ABOUT SHARPE PRITCHARD
We are a national firm of public law specialists, serving local authorities, other public sector organisations and registered social landlords, as well as commercial clients and the third sector. Our team advises on a wide range of public law matters, spanning electoral law, procurement, construction, infrastructure, data protection and information law, planning and dispute resolution, to name a few key specialisms. All public sector organisations have a route to instruct us through the various frameworks we are appointed to. To find out more about our services, please click here.
|
|
OUR RECENT ARTICLES
April 01, 2026
The ERA – Benefits and Working ConditionsCatrin Mills and David Leach provide an overview of the key changes within the Employment Rights Act to workplace benefits and working conditions.
April 01, 2026
£150m Clean Maritime Grant Competition Opens – Critical Subsidy Control Steps for ApplicantsBeatrice Wood and Oliver Slater discuss the second round of “Zero Emission Vessels and Infrastructure 2 (ZEVI 2): Energy Efficiency”, offering up to £150 million in grant funding for large‑scale demonstration projects.
April 01, 2026
Failure by Employers to Keep Holiday Records Becomes a Criminal Offence From April 2026Julie Bann, Catrin Mills, David Leach and Christian Grierson talk through the upcoming changes to employment law.
April 01, 2026
Why I Wanted to Explore Intensity of Review Across the UK and New ZealandJack Trevella shares his experience of the difference in UK vs New Zealand courts on the doctrine of reasonableness.
|
|
OUR KEY LOCAL GOVERNMENT CONTACTS
|
||
|
Partner 020 7406 4600 Find out more |
||
|
Partner 020 7406 4600 Find out more |
||
|
Rachel Murray-Smith Partner 020 7406 4600 Find out more |









Catherine Newman
