Local Government Lawyer

GLD March 26 Planning Lawyer Adhoc Banner 600 x 100 px 1

GLD Data Vacancies


When the Procurement Act 2023 came into force, one of the most immediate practical questions for practitioners was how the courts would approach remedies, particularly automatic suspension.

Many, myself included, anticipated continuity. The assumption was that, notwithstanding the new statutory wording, the courts would continue to reach outcomes broadly aligned with the familiar American Cyanamid framework under the Public Contracts Regulations 2015. That framework, in practice, often favoured contracting authorities. Suspensions were frequently lifted, as damages were considered an adequate remedy.

The first reported decision under the Act, ParkingEye Ltd v Velindre University NHS Trust [2026] EWHC 1019 (TCC), suggests that assumption may need revisiting.

In ParkingEye, the court refused to lift the automatic suspension.

Whilst this case alone does not establish a trend, it does raise an important question: Are we seeing the beginnings of a shift toward a more claimant protective approach to interim relief in procurement challenges?

Facts of the Case

The defendants (Velindre NHS Trust and Cardiff & Vale UHB) sought to lift the automatic suspension under section 102 of the Procurement Act 2023, which prevented them from entering into a contract for NHS car park management services.

The claimant, ParkingEye, was the incumbent provider and had issued proceedings during the standstill period, thereby triggering the suspension.

The substantive challenge alleged multiple breaches of the Procurement Act 2023, including:

  • Misidentification of the contracting authority
  • Material errors in the stated contract value
  • Failures in the design
  • Unclear / undisclosed evaluation criteria, resulting in unfair treatment of bidders

As is often the case at this stage, the court was not determining those issues, but instead deciding whether the contract could proceed before they were resolved.

A Clear Break from American Cyanamid

The most important aspect of the judgment is the court’s unequivocal recognition that section 102 introduces a genuinely new test.

As the judge put it:

... several matters would seem to provide a clear indication that the new test is intended to be substantively and not merely formally very different, in both its method and its effect...

That statement should not be overlooked.

The court went further, setting out a structured summary of the new approach. The key points of such summary are as follows:

“The test requires the court to balance the public interest and the interests of suppliers…

The adequacy of damages… no longer has the significance it had…

… the public interest [includes] that, where the lawfulness of a proposed contract award is in dispute, the contract should not be awarded until the dispute has been resolved…

… lifting of the suspension will generally require… a very persuasive countervailing public interest or some overriding matter of private interest…”

This is the doctrinal heart of the case.

Three features stand out:

  1. Adequacy of Damages is No Longer King

Under American Cyanamid, adequacy of damages was often outcome determinative. If damages were sufficient, the suspension typically fell away. That is no longer the position.

The judge accepted, on the facts, that:

  • Damages would likely be adequate
  • Quantification would not be unduly difficult
  • Reputational damage arguments were weak

Yet crucially, that did not decide the case. Instead, adequacy of damages is now one factor among several, and not the dominant one. This is a meaningful recalibration. It removes what was historically the most powerful argument available to contracting authorities on applications to lift.

  1. Public Interest is Re-centred and Reframed

The court placed significant weight on the statutory public interest factors, particularly:

  • The importance of lawful procurement; and
  • The principle that contracts should not be entered into where lawfulness is genuinely in dispute.

The judge articulated this in striking terms:

The public interest includes “that, where the lawfulness of an award… is disputed, the contract should not be awarded until that dispute has been resolved.

This is a notable shift in emphasis. Under the previous regime, public interest often manifested as an argument about urgency or service delivery and came into play relatively late in the analysis. Under section 102, it sits at the centre of the exercise.

Although the new contract promised certain operational improvements, for example enhanced systems and revenue sharing, these were described as modest and insufficient to outweigh the public interest in maintaining the suspension, particularly as the judge noted that these could largely be achieved whilst the suspension is in place.

  1. A High Bar for Lifting Suspensions

Perhaps the most practically important takeaway is the court’s articulation of what is required to lift a suspension.

The judgment suggests that lifting will ordinarily require:

... either a very persuasive countervailing public interest or some overriding matter of private interest.”

That is a high threshold. Notably, it is framed in terms of exceptionality, not a routine balancing act.

This represents a significant detour from the prior regime, where suspensions were often treated as temporary obstacles to be removed unless strong reasons existed to maintain them.

Application to the Facts

Applying those principles, the court’s reasoning can be distilled as follows.

On the public interest side of the balance:

  • There was no interruption to the ongoing provision of services.
  • The case did not engage the kind of urgent or critical public interest contemplated by the statute (such as defence, security, or a genuine risk to service continuity).
  • The benefits of the new contract were, in the court’s view, relatively modest, with some capable of being achieved during the suspension period.

On the other side:

  • The court did not undertake any detailed assessment of the merits, but proceeded on the basis that the dispute should properly be resolved before contract award.
  • There was a clear public interest in ensuring that public contracts are not entered into where their lawfulness remains in issue.

The conclusion followed:

The courts [should not] too lightly lift the suspensions.

Accordingly, the suspension remained in place.

A 1–1 Record – But What Does That Really Tell Us?

It is tempting, at this stage, to draw conclusions from the “scorecard”:

  • One major reported case
  • One refusal to lift

But that would be premature.

Procurement cases are intensely fact sensitive, and a single decision does not establish a trend. What it does provide, however, is something arguably more valuable:

  • A judicial blueprint for applying section 102
  • A clear statement that the new test has real teeth
  • A departure, in tone and structure, from the prior regime

What Is Genuinely New Here?

The most important development is not that the suspension was upheld. It is why.

The case signals that:

  1. Automatic Suspension is a Substantive Protection

It is no longer merely a procedural pause pending inevitable lifting. It is a meaningful mechanism to preserve the integrity of procurement challenges.

  1. The Court is Prepared to Let Challenges “Breathe”

There is a clear judicial willingness to allow disputes about legality to be resolved before irreversibility occurs (i.e. contract award).

  1. Contracting Authorities Face Real Litigation Risk

Authorities can no longer assume that the balance of convenience will favour them, even where:

  • Services continue uninterrupted
  • Damages are available

That is a significant shift in litigation dynamics.

A Subtle but Immediate Shift in Leverage

Even without a settled line of authorities, the practical implications could be immediate.

If public bodies perceive that suspensions may now be more difficult to lift, we are likely to see:

Pre-Award Phase

  • Increased scrutiny of assessment processes
  • Greater emphasis on audit trails and documentation
  • Lower tolerance for procedural ambiguity

Post-Award Phase

  • More cautious decision making when faced with a challenge
  • Increased willingness to engage in early resolution
  • Greater reluctance to “push through” to contract
  • Stronger negotiating position for challengers
  • Increased strategic value in issuing proceedings during standstill and therefore an increase in challenges

In short, even without doctrinal certainty, behaviour may shift quickly.

The Dawn of a New Era?

Not quite: at least not yet.

ParkingEye is one case, on one set of facts. It does not establish a settled direction of travel. Future decisions may refine, limit, or even rebalance the approach.

But it does mark something important. It confirms that:

  • The Procurement Act 2023 is not simply a legislative rebranding exercise
  • Section 102 introduces a genuinely different analytical framework
  • The courts are willing, at least in appropriate cases, to give real effect to that framework

Perhaps most significantly, it reasserts a principle that had, in practice, become somewhat diluted:

Public contracts should not proceed where their lawfulness is genuinely in issue.

For now, that is enough to warrant attention.

Whether this becomes a pattern, or remains an outlier, will depend on the next wave of cases.

But if nothing else, ParkingEye ensures that automatic suspension is once again a remedy that both sides must take seriously.

Nicola Cullen is an Associate of Capital Law's Public Law & Regulatory team.

Must read

LGL Red line

Sponsored articles

LGL Red line

Unlocking legal talent

Jonathan Bourne of Damar Training sets out why in-house council teams and law firms should embrace apprenticeships.

Poll


 

Directory